[April 2018] Free Sharing Of Updated PK0-004 VCE And PDF Dumps From Lead2pass 115q

Free Updated Lead2pass PK0-004 Exam Dumps Download:

https://www.lead2pass.com/pk0-004.html

QUESTION 21
Which of the following is a definition of an RFP?

A.    A document sent to potential vendors to solicit a bid for a project
B.    A document sent to potential vendors to request information for skills and experience for a project
C.    A document sent to potential vendors to request a commitment for a project
D.    A document sent to potential vendors to solicit information that excludes pricing information for a project Continue reading “[April 2018] Free Sharing Of Updated PK0-004 VCE And PDF Dumps From Lead2pass 115q”

[March 2018] 2018 New Released CompTIA PK0-004 Exam Dumps Free Download In Lead2pass 115q

2018 Updated Lead2pass CompTIA PK0-004 Exam Questions:

https://www.lead2pass.com/pk0-004.html

QUESTION 11
If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

A.    The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
B.    The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report
C.    The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW; and then create a status report to provide to the project manager.
D.    The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review

Answer: B

QUESTION 12
Which documents does a vendor rely on to commit funding and resources to a project?

A.    SOW
B.    PO
C.    SU
D.    MOU

Answer: B

QUESTION 13
A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorm,TM of potential strategies.
Which of the following documents should the project coordinator use?

A.    Risk register
B.    Issue log
C.    Communication plan
D.    Status report

Answer: A

QUESTION 14
Which of the following describes how a project is related to a program?

A.    A program is a combination of multiple projects.
B.    A program contains an element of the project.
C.    A program is a part of a project.
D.    A program uses half of the project’s budget.

Answer: A

QUESTION 15
Which of the following is a key aspect of the Agile project management methodology?

A.    Test-driven
B.    Daily standup meetings
C.    Short project durations
D.    Defined list of requirements

Answer: B

QUESTION 16
Which of the following are examples of organizational change? (Choose two.).

A.    Relocation
B.    Scope
C.    Business process
D.    Schedule
E.    Risk event

Answer: AC

QUESTION 17
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?

A.    Project charter
B.    Project management plan
C.    Project statement of work
D.    Project schedule

Answer: B

QUESTION 18
The PMO is responsible for: (Choose two.),

A.    managing the project plan, scope, risk, and budget.
B.    contributing expertise, deliverables, and estimates of costs.
C.    setting standards and practices for the organization and providing governance.
D.    outlining consequences of non-performance and coordinating between disparate projects
E.    approving funding, developing the project schedule, and gathering high-level requirements

Answer: CD

QUESTION 19
Which of the following describes risk mitigation?

A.    The transfer of the risk to another entity or project inside or outside the organization, along with associated costs
B.    The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence
C.    The quantification of the risk in terms of how much the risk could potentially cost the project or parent organization
D.    The weighting or prioritization of the risk against all other identified risks within this project or others associated with it

Answer: B

QUESTION 20
A project manager has noticed poor attendance at status meetings. Which of the following strategies should the project manager use to improve attendance? (Choose two.)

A.    Provide an agenda before the status meeting
B.    Adhere to an agenda and scheduled time
C.    Add non-project-related items to the agenda
D.    Add and discuss new agenda items throughout the meeting.
E.    Discard the action items at the conclusion of the meeting.

Answer: AB

PK0-004 dumps full version (PDF&VCE): https://www.lead2pass.com/pk0-004.html

Large amount of free PK0-004 exam questions on Google Drive: https://drive.google.com/open?id=0B3Syig5i8gpDYzdieENjeXZuVlU

[January 2018] Lead2pass Provides Free PK0-004 Exam Dumps PDF 115q

Lead2pass Provides Latest Exam PK0-004 Dumps VCE For Free Downloading:

https://www.lead2pass.com/pk0-004.html

QUESTION 1
The project manager was asked to provide recommendations for the removal of a vendor.
A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)

A.    The issue log to show why the vendor should be replaced
B.    The team action items to show why the vendor should be replaced
C.    The scope statement to show why the vendor should be replaced
D.    A procurement plan to show why the vendor should be replaced
E.    A change management plan to have the vendor replaced Continue reading “[January 2018] Lead2pass Provides Free PK0-004 Exam Dumps PDF 115q”

[2017 New] Ensure Pass PK0-004 Exam By Training Lead2pass New PDF Dumps

2017 June CompTIA Official New Released PK0-004 Dumps in Lead2pass.com!

100% Free Download! 100% Pass Guaranteed!

Although the CompTIA PK0-004 dumps are very popular, Lead2pass offers a wide range of CompTIA PK0-004 exam dumps and will continue to release new study guide to meet the rapidly increasing demand of the IT industry.

Following questions and answers are all new published by CompTIA Official Exam Center: http://www.lead2pass.com/pk0-004.html

QUESTION 1
The project manager was asked to provide recommendations for the removal of a vendor.
A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation. Which of-the following should the project manager bring to the meeting to support this recommendation? (Select TWO)

A.    The issue log to show why the vendor should be replaced
B.    The team action items to show why the vendor should be replaced
C.    The scope statement to show why the vendor should be replaced
D.    A procurement plan to show why the vendor should be replaced
E.    A change management plan to have the vendor replaced

Continue reading “[2017 New] Ensure Pass PK0-004 Exam By Training Lead2pass New PDF Dumps”